FSNI Invests In Chilled DC

FSNI Invests In Chilled DC

A major new piece of infrastructure supporting supermarkets, wholesale customers, suppliers and communities across the Upper North Island has taken shape.

Construction has progressed on Foodstuffs North Island’s new chilled and frozen distribution centre in Māngere, Auckland.

The facility is being developed by Auckland Airport, the landowner and developer of the site, and will be leased by Foodstuffs once complete.

Foodstuffs North Island Chief Executive Chris Quin said the investment was about ensuring the co-operative’s local, family-owned stores and other customers have the infrastructure needed to support New Zealand’s future.

“Customers don’t often see what happens before products reach the supermarket shelf. Behind every full chiller and freezer is a supply chain that needs to work safely, efficiently and reliably to support customers and suppliers,” said Quin.

“This investment gives us the infrastructure we need for the next 25 to 35 years, helping us support our locally owned New World, PAK’nSAVE, Four Square and Gilmours stores, other retailers, suppliers and the communities they serve.”

Quin added that communities across the Upper North Island have grown, and demand for chilled and frozen products has grown with them. This facility will give them the room to grow while making it easier for more suppliers to connect with the network.

The project has become one of the largest supply chain investments Foodstuffs North Island has made and will more than double the co-operative’s chilled and frozen capacity.

Foodstuffs North Island Senior Development Manager David Boersen said the new facility will improve the way products move through the network.

“Behind every product on a supermarket shelf is a supply chain. The better that supply chain works, the easier it is for suppliers to work with us and the more reliable our service is for stores and customers,” he said.

This new distribution centre will improve product availability, reduce unnecessary handling, improve freight efficiency and help get products to stores more reliably.

The building has been designed with safety, efficiency and sustainability at the forefront, including:

  • Four large roof sections were built on the ground and lifted into place using eight of New Zealand’s largest mobile cranes, reducing the work required at height
  • A “box within a box” design, with an insulated chilled and frozen warehouse inside the main building structure
  • Modern refrigeration technology, including a CO₂ refrigeration system
  • Around 2.5 hectares of rooftop solar panels are generating approximately 2MW of electricity
  • Infrastructure designed to support future technology, including electric trucks and automated material handling equipment
  • A design target of achieving a 5 Star Green Star rating

Construction has progressed to programme, with the building expected to be handed over by Auckland International Airport in the final quarter of 2027.

Cooling, testing and commissioning will follow, with the facility expected to be operational in the first quarter of 2028.

The new distribution centre will include:

  • 24,821 square metres of warehouse space
  • Capacity for 27,656 pallets with racking up to 12 metres high
  • 27 modern loading docks and onsite parking for up to 30 trucks
  • Dedicated chilled (+2°C) and frozen (-24°C) storage areas
  • A 1.96MW rooftop solar array and backup generation system

Foodstuffs North Island will lease the facility from Auckland Airport through an initial 25-year lease.